A is 75%efficient than B .if A can do a complete work in 10 days then B can do the same work in​

Question

A is 75%efficient than B .if A can do a complete work in 10 days then B can do the same work in​

in progress 0
Piper 2 months 2021-09-25T05:52:38+00:00 2 Answers 0 views 0

Answers ( )

    0
    2021-09-25T05:53:40+00:00

    Answer:

    40 days

    Step-by-step explanation:

    B can do the work in 40 days

    ie. B can do work in 100min so A can do it in 25 min

    A/B= 25/100=1/4

    now take the given question

    1/4=10/x

    x=40

    therefore 40 days

    0
    2021-09-25T05:53:49+00:00

    Answer:

    40 Days

    Step-by-step explanation: